Client Need

Trafikverket is building a comprehensive infrastructure project in E4 to support the development in a rapidly growing Stockholm region.

Project Overview

Infinity Mätkonsult participated in the building of concrete tunnels, widenings, ponds, walls, asphalt works, to enable in the future the circulation of around 100,000 vehicles per day.

Surveying the construction works

Surveying supports construction from excavation through tunnel works. Precision instruments help teams check positions and levels on site.

Surveying instrument set up at an excavation site
Surveying at the construction site
Surveying equipment and crew beside a retaining structure
Surveying beside a retaining structure

Excavation and retaining structures

Road widening and excavation works require careful coordination around the existing road and temporary retaining structures.

Tunnel construction site in winter
Tunnel construction in winter conditions
Interior of a concrete tunnel under construction
Concrete tunnel works

Tunnel construction

The project included concrete tunnel works at different stages, from structural reinforcement to the construction of the tunnel lining.

Aerial view of tunnel construction beside an active road
Tunnel works alongside the road
Surveyor working inside an underground tunnel
Surveying inside the tunnel

Surveying around active infrastructure

Work around tunnel approaches and existing traffic calls for accurate measurements coordinated with ongoing construction activity.

Close-up of a red surveying prism
Surveying prism
Aerial view of tunnel construction and road infrastructure
Construction and infrastructure overview

Excavation overview

The aerial view shows the scale of the excavation and the retaining structures used at the site.

Aerial view of an excavation with retaining structures
Excavation viewed from above

Challenges

Widening of the existing roads, two concrete tunnels (one on each side of the existing E20 road at the Förbifart connection), emergency exits, rock tunnels, rock wire cutting, comprehensive ground reinforcement work as sheet piles, curtain grouting, rock blasting, rock bolting, polluted soil excavation, sewage system and VA, bike trails.

Project FSE 215 Executed Quantities

Rock Excavation: 70,000 m³
Soil Excavation: 30,000 m³
Concrete: 20,000 m³